Introduction
Poor weather can seriously affect the performance of an Access Platform Decking system. In line with the requirements of the Work at Height Regulations 2005, systems require inspection following adverse weather and prior to use. If any defects are identified, remedial action and a further inspection will be required prior to a Handover Certificate being issued.
Inspection
An inspection following adverse weather should be carried out by a competent person, the defects reported and access to the system prohibited until they have been rectified and a Handover Certificate issued.
The inspection of an Access Platform Decking systems comprises of two parts: an inspection from beneath the system and an inspection from above the system. If any defect is found during any part of either inspection, the system should be removed from service.
See the Download to read more…